To complete a job, ‘A’ requires 12 days. For the same job, ‘B’ requires 20 days to complete the job. Both of them worked together for 3 days and then A left the job. To complete the remaining job, how many days ‘B’ will require?
Options
Option A
18
Option B
15
Option C is correct
12
Option D
10