A contract related to cleaning debris around the construction work, specifies penalty in completion of work beyond certain days as follows: ₹ 250 for 1st day; ₹ 310 for 2nd day; ₹ 370 for the 3rd day and so on. If the contractor pays the fine amount ₹ 6960 then select the number of days he delayed the work.